Status. Proposed design only. Nothing in this vault is DG client approval. No application, service or test has been executed; every scenario is Not executed. Fees and dates are open.
Gap and risk register
Seeded from the vault’s own statements. Owner column names a role to confirm, never a person DG has not named.
| ID | Gap or risk | Source | Effect | Next step |
|---|---|---|---|---|
| G-01 | All 25 DG decisions Q01 to Q25 are pending | Decision-Index | Dependent behaviour and oracles blocked | Owner obtains DG decisions; see Decision-Gates |
| G-02 | Start conditions unmet (statement of work, kickoff checklist, accounts, staffing) | Implementation-Order-Overview | Application scaffolding stays locked | Owner confirms (G-3 in the bootstrap guide) |
| G-03 | Two dedicated engineers is an assumption, not a fact | Implementation-Order-Overview | Schedule risk | Confirm staffing |
| G-04 | Identity and email vendors, hosting and region unknown | Q09 | Real adapters cannot be built | Code to Integration-Ports |
| G-05 | Retention and deletion policy unknown | Q09 | No live data allowed | Keep synthetic data only |
| G-06 | Load, recovery and accessibility targets unagreed (A10 unverified) | Acceptance-Gates-A01-A11 | T39 and T40 cannot be judged | Agree targets first |
| G-07 | No penetration test, load test or restore drill performed | Status-and-Honesty | Security and recovery claims unproven | Plan in Step 10 |
| G-08 | Physical schema not final | Data-Model | Migration churn | Settle during Steps 01 to 04 |
| G-09 | A11 coverage unverified; annex awaits DG confirmation | A11-Language-and-Email-Checklist | Language gate open | Step 11 checklist |
| G-10 | Stack profile is an engineering proposal, not a vault requirement | ADR-0001-Stack-Profile | Owner may change it | Owner accepts or revises the ADR |
| G-11 | Independent review of bootstrap PRs pending where marked | operating-contract | Review state unknown | Run reviewer |
Change history
| Date | Change |
|---|---|
| 2026-10-20 | Created (bootstrap Phase 2) |