Status. Proposed design only. Nothing in this vault is DG client approval. No application, service or test has been executed; every scenario is Not executed. Fees and dates are open.

Gap and risk register

Seeded from the vault’s own statements. Owner column names a role to confirm, never a person DG has not named.

IDGap or riskSourceEffectNext step
G-01All 25 DG decisions Q01 to Q25 are pendingDecision-IndexDependent behaviour and oracles blockedOwner obtains DG decisions; see Decision-Gates
G-02Start conditions unmet (statement of work, kickoff checklist, accounts, staffing)Implementation-Order-OverviewApplication scaffolding stays lockedOwner confirms (G-3 in the bootstrap guide)
G-03Two dedicated engineers is an assumption, not a factImplementation-Order-OverviewSchedule riskConfirm staffing
G-04Identity and email vendors, hosting and region unknownQ09Real adapters cannot be builtCode to Integration-Ports
G-05Retention and deletion policy unknownQ09No live data allowedKeep synthetic data only
G-06Load, recovery and accessibility targets unagreed (A10 unverified)Acceptance-Gates-A01-A11T39 and T40 cannot be judgedAgree targets first
G-07No penetration test, load test or restore drill performedStatus-and-HonestySecurity and recovery claims unprovenPlan in Step 10
G-08Physical schema not finalData-ModelMigration churnSettle during Steps 01 to 04
G-09A11 coverage unverified; annex awaits DG confirmationA11-Language-and-Email-ChecklistLanguage gate openStep 11 checklist
G-10Stack profile is an engineering proposal, not a vault requirementADR-0001-Stack-ProfileOwner may change itOwner accepts or revises the ADR
G-11Independent review of bootstrap PRs pending where markedoperating-contractReview state unknownRun reviewer

Change history

DateChange
2026-10-20Created (bootstrap Phase 2)